Delayed Apartment Handover: Court Orders NIS 30,000 a Month
Real Estate

Delayed Apartment Handover: Court Orders NIS 30,000 a Month

The Olam Editorial Team
The Olam Editorial Team
Editorial Team, led by Publisher Ronn Torossian
Nov 22, 2026, 3:01 PM EST

A Tel Aviv developer and his company must pay buyers NIS 30,000 a month until a delayed apartment is delivered, the Kfar Saba Magistrate's Court ruled in an interim decision reported by Calcalist on November 22, 2026. The buyers purchased a NIS 9 million duplex in a TAMA 38/2 project, and delivery is about 20 months late.

Last updated: November 22, 2026

What did the court order?

The court ordered the developer's company and its manager and controlling shareholder, jointly and severally, to pay the buyers NIS 30,000 a month until the apartment is lawfully delivered. Judge Hagit Bulmash issued the interim ruling on Thursday, before any final judgment in the main case, according to Calcalist.

The payments run from October 20, 2026, the date the buyers applied, and continue until an occupancy permit, known in Israel as Form 4, is issued and the apartment is delivered. The company named in the case is Bereshit HaShachar Investments and Assets Dizengoff 27 Tel Aviv, as Calcalist reported. Any money paid is credited against damages if the buyers win the main case.

What are the facts of the purchase?

The buyers, a couple with children, signed their purchase contract on June 18, 2024 for a NIS 9 million duplex in a TAMA 38/2 urban renewal project in Tel Aviv. The contract set delivery for February 18, 2025, and no occupancy permit has been issued by the Tel Aviv municipality, Calcalist reported.

ItemDetail as reported by Calcalist
Contract signedJune 18, 2024
PriceNIS 9 million including VAT
Contractual delivery dateFebruary 18, 2025
DelayAbout 20 months
Paid by the buyersNIS 8.1 million (about 90%), into the project's escrow account
Buyers' claimed monthly costsAbout NIS 25,000 in financing, including a balloon loan and mortgages
Occupancy permit (Form 4)Not yet issued

The buyers told the court they cannot sell their current home while waiting. Calcalist also reported that some units in the building are occupied without a Form 4.

What does the developer say?

The developer and his company say a Form 4 is expected within weeks and blame the delay on the buyers' own actions. According to Calcalist, they point to the buyers' complaints to the municipality and an administrative petition, dispute the buyers' valuation of the rent, and argue that the buyers are in breach of the contract.

Those claims have not been decided. The ruling is interim, and the court did not rule on who is responsible for the delay.

What conditions did the court attach?

The court attached three conditions to the monthly payments, according to Calcalist.

  • The buyers must deposit a personal undertaking to repay the money, with linkage and interest, if their claim fails or yields less.
  • The defendants may ask the court to reduce the amount, using a valuation report or comparable rental agreements.
  • The defendants must pay NIS 10,000 in legal costs.

The undertaking means the payments are an advance, not a final award. If the main case ends in the developer's favor, the buyers would have to return the money.

Why does the ruling matter for buyers?

The ruling matters because it shows a court will order monthly payments to buyers before it decides who caused a delay. Judge Bulmash wrote, as translated by Calcalist, that refusing interim monetary relief "undermines the legislature's intent" to give buyers monthly remedies.

The buyers' lawyer, Lior Har-Tzvi, called it a decision of cross-cutting importance for buyers from contractors, Calcalist reported. It is a single magistrate's court decision, so its weight in other cases is untested.

The case comes as developers face other pressure in the same market. Olam reported on November 22 that, according to Finance Ministry Deputy Chief Economist Galit Ben Naim, Tel Aviv and Bat Yam developers hold about 15,000 unsold apartments. A late handover and unsold stock are separate problems, but both put pressure on developers.

Frequently asked questions

Is the NIS 30,000 monthly payment a final judgment?

No. It is an interim ruling issued before a final judgment. The amount is credited against any damages awarded later, and the buyers must undertake to repay it if their claim fails or yields less.

What is a Form 4 in Israel?

Form 4 is the occupancy permit for a building. In this case the buyers say they cannot lawfully receive the apartment until the Tel Aviv municipality issues it.

When was the apartment due to be delivered?

The contract set delivery for February 18, 2025. Calcalist reported a delay of about 20 months as of the ruling.

Who reported the ruling?

Calcalist reporter Lital Dubrovitsky reported the ruling on November 22, 2026. Olam has not seen the court decision itself.

How we report: Olam stories draw on public filings, company disclosures and named sources, checked by our editors. Read our methodology · Corrections

Founders & Companies

All coverage →

Fintech & Public Markets

All coverage →

Israeli Media, Entertainment & Gaming

All coverage →
888 Holdings: The Two Brother Pairs Behind It
Israeli Media, Entertainment & Gaming · Nov 18, 2026, 3:00 PM EST
888 Holdings: The Two Brother Pairs Behind It

Two pairs of Israeli brothers built 888 Holdings from second mortgages into a London-listed gambling giant. Two of the four founders are now…